Point Cook Building
Inspections

Tie-down bolts on a Point Cook frame

Drawn on the engineering, and sometimes never fitted.

Owner Inspections · Point Cook 3030 · 2026-03-17

In short: The bolts holding your frame down are nominated on a drawing. Somebody has to check the drawing.

What a tie-down does

It holds the frame to the slab against wind uplift. The engineering nominates M10 or M12 bolts at specific locations.

What we have found

Bolts shown on the engineering that were not installed at the time of the frame inspection.

Why nobody catches it

Nobody on site is comparing the frame to the engineering. The carpenter builds what is in front of them, and a missing bolt looks like nothing at all.

The related findings

Beam connections not matching the detail, and bracing shown on the plans and left out.

What to do

Book the frame inspection and give us the engineering. The comparison is the whole value.

Written by the Owner Inspections team from inspections carried out in Point Cook. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More new construction stage inspections guides for Point Cook

All guides →

Book a building inspection in Point Cook

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Point Cook owners ask about this

Is a missing bolt serious?

It is classified as a structural safety item, because uplift resistance is what it provides.

Can it be added later?

Before lining, easily. After, it means opening walls.

Who is responsible?

Your builder, held to the engineering they were issued.

Do you certify the frame?

No. We report against the drawing; the engineer certifies.

CallGet a Free Quote